If you want the jaw crusher have a better crushing operation, you should operate the machinery rightly, then the jaw crusher could play its role during the crushing operation.

1. Preparations before starting the jaw crusher:

a. Before starting the crusher, we should carry out strict check of crusher, whether the bolts of fasteners are loose and the abrasion of parts is too large or not.

b. We should take measures to tighten the bolts and change the parts as soon as possible in order to ensure the normal operation of crusher.

2. The starting of jaw crusher:

a. The machine should be started before inspection, and proved the machine and the transmission part are n good condition.

b. Jaw crusher can only start under no load.

c. After starting, if you find some abnormal situations, you should stop it immediately. When everything is in control, you can start the machine again.

3. The maintenance and use of the jaw crusher:

a. Flywheel and eccentric support bearing is often using spherical roller bearings. Bearing working environment is extremely harsh. Bearings must support enormous impact load, abrasive water and high temperature, though the working environment is extremely harsh, the jaw crusher still need to work very reliably, this is a key element to ensure the productivity.

b. When we stopping the impact crusher, we should be accordance with the prescriptive requirements of the parking order. We should find the abrasion and change the hammer as soon as possible.

c. In order to make a better static balance of the rotor, we could select the new hammer carefully. The protective panel should be changed immediately to avoid the lining and back panel sliding off.

4. The lubrication work of jaw crusher:

a. We should notice the lubrication work of friction surface timely, and add lubrication oil after each working eight hours. We also need change lubrication grease each three month.

b. Please use the clear petrol or clean the bearing carefully when changing the oil .The lubrication grease we added into the bearing is half of the total volume.

Related Articles:
Service Matters Gradually with Enterprise ProsperityResearch on the role of Jaw crusher in limestone production lineEnvironmental Jaw Crusher Reuses Blast Furnace Slag Hongxing Jaw Crusher Is Moving Toward Technical PinnacleWhat Elements Restrict Production Efficiency of Jaw Crusher?Most Significant Application of Jaw Crusher

| Contact Us | Sitemap | Sitemap.xml | RSS
Tanxiang Road, High & New Technology Industries Development Zone of Zhengzhou, China